The awful, wet weather this spring has put the Revive I-5 project so far behind schedule that holiday weekends are now in play for lane closures.

There were supposed to be five weekends off when the work to replace 35 old expansion joints on southbound I-5 began earlier this year:  Memorial Day, University of Washington graduation, Juneteenth, 4th of July, and Labor Day.

But the Washington State Department of Transportation’s Amy Moreno said the weather put them so far behind, that those weekends off are changing.  “We’ve had two weekends of work so far, and we had two weekends we had to postpone because of rain, and one weekend